Prevoius Weekly Reports

   Weekly progress report as on 09.11.2012
    
Progress Report For Mooledam ROB for the week ending on 10-11-2012  
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE 27 10 17 0 6 4 2 4 0  
2 PILE CAP 9 0 9 0 1 0 1 2 0  
                       
                       
  Availbility of Men                     
  Date 11-05-2012 11-06-2012 11-07-2012 11-08-2012 11-09-2012 11-10-2012        
  Nof labours 15 15 18 24 24          
                       
  Material Stocking Status                  
    Required Available Remarks              
  Fine aggregate {cft} 400 100                
  Cement(bag) 250 510                
  Steel in T 3 10                
  Coarse Aggreagate (cft) 400 100                
                       
  Utility shifting                    
  Utilities to be shifted   Remarks                
  BSNL   NOT SHIFTED                
  KSEB   NOT SHIFTED                
  KWA   NOT SHIFTED                
  Others                    
 