   Weekly Progress Report as on 09.11.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 97% 3% 3% 3.00% 0.00% 3.00% 2.00%   Friction slab complete for RHS and LHS,slow work at friction slab caping.
10 RE/RC  WALL PADANNA SIDE 100% 57% 43% 5% 5.00% 5.00% 5.00% 10.00%   ONE layer erected at LHS.Earth filling and rolling IP.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 80.00% 20% 0 0.00% 0.00% 0.00% 10.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 80% 20% 0.00% 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works HELD UP due to shortage of labour.
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side,Work in progress for 21m drainage.Shortage of labour affected the remaining works.
                       
                       
                      DR Work complete for 4m service road and 7m road.
                       
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 03-11-12 04-11-12 05-11-12 06-11-12 07-11-12 08-11-12 09-11-12      
  No of labours 12 12 12 15 15 13 13      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 100 600              
  Steel(MT) 2 8              
                       
                       
  Utility shifting              
  Utilities to be shifted Status Remarks                
  BSNL shifting complete at Padanna side RE Panel area.OFC was broken on 16-10-12 and repaired.OFC work in progress.            
  KSEB   electric post infront of unity hospital  need to be shifted urgently,currently not affecting the works.AXE and AE visited the site on 27-09-12.Lines over RC Wall Padanna side shifted.            
  KWA Repaired the pipelines at Padanna RE Panel area.            
  Others                    
 
Back
 
    
VIEW OF CHR SIDE

    
    
PADANNA RE PANEL AREA

    
    
DR COMPLETE FOR 7M ROAD AT CHR SIDE

    
    
CHR SIDE DRAINAGE SHUTTERING IP

    
 
 
 

 

 

 

 

 

 

 