   Weekly Progress Report as on 02.11.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 17 4 - 1 2 0 0
6 Hand Rails 21 9 12   1 1 0 2
7 Expansion Joint 21 6 15   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
9 RC wall - Kanjipura side 100%       8% 8% 0% 10%
                   
Date 27.10.12 29.10.12 30.10.12 31.10.12 01.11.12 02.11.12      
Climate Pleasant Pleasant Pleasant Rain Rain Pleasant      
No. of labours 60 60 60 55 55 55      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 26 m3              
Coarse Aggregate 24 m3 28 m3              
Cement 150 bags 200 bags              
Steel 25 MT 31 MT              
 
Back
 
    
STAGING WORKS IN P9-P10

    
    
RC WALL RAFT CONCRETING IN KANJIPURA SIDE

    
    
BEAM REINFORCEMNT WORKS IN P7-P8

      
 

 

 

 

 

 

 

 