   Weekly Progress Report as on 02.11.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 01.11.12 Balance  work up to 01.11.12 Cumulative delay in Qty up to 01.11.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 0 0 0 0 completed
2 PILE Palarivattom side(railway portion) 6 6 0 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0 completed
4 PILE vytilla side(railway portion) 6 6 0 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
6 PILE CAP Palarivattom side(railway portion) 1 1 0 0 0 0 0 0 completed
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed
8 PILE CAP vytilla side(railway portion) 1 1 0 0 0 0 0 0  
9 PIER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
10 PIER Palarivattomside(railway portion) 1 1 0 0 0 0 0 0 completed
11 PIER Vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0  
13 PIER  CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed
14 PIER  CAP Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed
15 GIRDER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0  
16 GIRDER Vytila side(Approach portion) 9 8 1 0 0 0 0 0  
17 DECK SLAB Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0  
18 DECK SLABVytila side(Approach portion) 9 7 2 0 0 0 0 0  
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0  
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0  
21 RE WALL PANEL CASTING 351 351 0 0 0 0 0 0  
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0  
21 RE WALL Panel erection Palarivattom 100% 75% 0.25 0.3 100% 0% 25% 100%  
21 RE WALL Earth filling PALARIVATTOM 100% 35% 0.65 73 100% 8% 65% 50%  
22 Rly Pile Load test 1 1 0 0 1 1 0 0  
 