   Weekly report as per 02-11-2012
    
Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
Pile 79 21 58 43 3 0 46 3 42  
Pile Cap 12 0 12 12 0 0 9 1 49  
Pier 12 0 12 12 0 0 9 0 55  
Pier Cap 12 0 12 6 0 0 9 0 63  
Pedestals 12 0 12 6 0 0 9 0 66  
RE Wall 4 0 4 0 0 0 0 0 322  
Girder 11 0 11 0 0 0 0 0 261  
Deck Slab  11 0 11 0 0 0 0 0 271  
Hand rail Curb & Expansion Joints 11 0 11 0 0 0 0 0 281  
Drain spouts :               338  
Elasto -meric Paint :               381  
 