PROGRESS OF ROB and ROAD WORK AS ON 26-10-2012.
|
|
Description
|
Completed/ Progress
|
Remarks
|
IV
|
ROB at Parappanangady
|
|
|
|
Pier cap (Total no of pier Cap- 21)
|
Completed
|
21 NOS COMPLETED
|
|
RE Wall panel casting ( total600 nos)
|
Completed
|
Errection completed.
|
|
Slab calicut side (total 10 nos )
|
Completed
|
10 nos, adjacent span completed.
|
|
slab NH side ( 11 nos)
|
Completed
|
11 nos,adjacent span completed.
|
|
Retaining wall NH side
|
completed
|
completed
|
|
Retaining wall calicut side
|
completed
|
completed
|
|
Dirt wall AP2 concreting
|
completed
|
Done 100%
|
|
Dirt wall AP1 concreting
|
completed
|
Done 100%
|
|
Handrail casting
|
completed
|
1400 nos completed.
|
|
Adjacent span RP1-P9
|
completed
|
completed.
|
|
Adjacent span RP4-P10
|
completed
|
completed.
|
|
Handrail fixing
|
completed
|
completed..adj; span pending
|
|
NH side RE panel errection
|
completed
|
100% completed.
|
|
RE wall work calicut side.
|
completed
|
100% completed.
|
|
expansion joint
|
completed
|
completed.adj; span NH side balance.
|
|
painting-slab
|
completed
|
Existing structures completed (adjacent span balance ).
|
|
RAILWAY PORTION
|
|
|
|
Pilling work
|
Completed
|
piling completed.
|
|
RP1
|
In progress
|
pier ,piercap completed.
|
|
RP2
|
In progress
|
pier & piercap completed.
|
|
RP3
|
In progress
|
pier & piercap completed.
|
|
RP4
|
In progress
|
pier &piercap completed.
|