   Weekly Progress Report as on 26.10.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 17 4 - 0 0 0 Beam reinforcement
6 Hand Rails 21 8 13   2 1 1 2
7 Expansion Joint 21 6 15   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 20.10.12 22.10.12 23.10.12 24.10.12 25.10.12 26.10.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 60 60 55 55 55 55      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 26 m3 30 m3              
Coarse Aggregate 28 m3 32 m3              
Cement 170 bags 300 bags              
Steel 25 MT 30 MT              
 
Back
 
    
VIEW OF SLAB AT KUTTIPURAM SIDE

    
    
RC WALL VIEW AT KUTTIPURAM SIDE

    
    
BEAM REINFORCEMENT WORKS IN P7-P8

      
 

 

 

 

 

 

 

 