Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887802
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 26.10.2012
    
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile  36 7 29 0 0 0 0 0  
 
Back
 
    
CONCRETING AT P3

    
    
BORING AT P3

      
 

 

 

 

 

 

 

 