Airport Seaport Road Phase II (NAD to Mahilalayam)
 
Name Airport Seaport Road Phase II (NAD to Mahilalayam)
District Ernakulam
Administrative Sanction Details GO(Rt)No.1656/2016/PWD dated 02.12.2016
 Budget and Funding details KIIFB Funding
Length of Bypass 6600 m
Right Of Way 45 m
KIIFB Sanctoned Amount 437.28 Crores
Present Status LA requisition submitted to District Collector. Survey works started. But stopped due to outbreak of Covid-19. Contigency Charge deposited to LAO.
 

 

 

 

 

 

 

 

 

 