Prevoius Weekly Reports

   weekly progress as on 19.10.2012
    

 

Sl No  Activity Description  Total Quantity Cumulative progress upto 19.10.12 Balance  work up to 19.10.12 Cumulative delay in Qty up to .19.1012 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 0 0 0
7 PIER  CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
  PIER  CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
8 GIRDER Pettah side(Approach portion) 4 3 1          
9 GIRDER Anayara side(Approach portion) 4 3 1          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
12 RT Wall Pettah side(Approach portion) % 100 100 0          
13 RT Wall Anayara side(Approach portion) % 100 100 0               Kerb Reinforcement
14 RE Wall Panel Casting Pettah side(Approach portion) 400 400 0         Friction Slab 
15 RE Wall Panel Casting Anayara side(Approach portion) 400 400 0          
16 RE Wall Panel Erection Pettah side(Approach portion) 400 400 0          
17 RE Wall Panel Erection Anayara side(Approach portion) 400 400 0          
18 Expansion Joint(Pettah side) 4 0 4          
19 Expansion Joint(Anayara side) 4 3 1           
 
Back
 
    
HAND RAIL FIXING ANAYARA SIDE.

    
    
HAND RAIL CASTING PETTAH SIDE.

    
    
HAND RAIL CASTING PETTAH SIDE

    
    
FRICTION SLAB PCC

    
 
    
APPROACH ON ANAYARA SIDE

      
 

 

 

 

 

 

 

 