Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
94% |
6% |
5% |
5.00% |
2.00% |
3.00% |
5.00% |
|
Friction slab complete for RHS,12 m complete at LHS. |
10 |
RE/RC WALL PADANNA SIDE |
100% |
55% |
45% |
5% |
5.00% |
2.00% |
3.00% |
5.00% |
|
Excavation complete,dewatering and mud removal in progress,ONE layer erected at LHS. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
7 |
2 |
0 |
0 |
0 |
0 |
0 |
|
complete except AP2 and P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
0 |
0 |
0 |
0 |
0 |
|
complete except AP1 and P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
80.00% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
80% |
20% |
0.00% |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
18 |
HANDRAIL PADANNA SIDE |
100% |
79% |
21% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Grinding and finishing works HELD UP due to shortage of labour. |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
Drainage works complete for 56 m at chr side,excavation and PCC complete for another 21 m. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DR Work complete for 4m service road and work IP for 7m road at chr side. |
|
|
|
|
|
|
|
|
|
|
|
Site cleaning works in progress |
19 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
20 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
13-10-12 |
14-10-12 |
15-10-12 |
16-10-12 |
17-10-12 |
18-10-12 |
19-10-12 |
|
|
|
|
No of labours |
16 |
16 |
19 |
16 |
16 |
11 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
160 |
450 |
|
|
|
|
|
|
|
|
Steel(MT) |
1.5 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
shifting complete at Padanna side RE Panel area.OFC was broken on 16-10-12 and repaired. |
|
|
|
|
|
|
|
KSEB |
|
electric post infront of unity hospital and lines over RC Wall area at Padanna side need to be shifted urgently,currently not affecting the works.AXE and AE visited the site on 27-09-12. |
|
|
|
|
|
|
|
KWA |
Repaired the pipelines at Padanna RE Panel area. |
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|