Prevoius Weekly Reports

   weekly progress as on 12.10.2012
    

 

Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 15 6 - 1 1 1 1
6 Hand Rails 21 8 13   2 1 1 2
7 Expansion Joint 21 4 17   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 06.10.12 08.10.12 09.10.12 10.10.12 11.10.12 12.10.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 76 70 75 76 78 78      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 23 m3 26 m3              
Coarse Aggregate 22 m3 28 m3              
Cement 175 bags 400 bags              
Steel 26 MT 32 MT              
 
Back
 
    
VIEW OF SLAB AT KUTTIPURAM SIDE

    
    
RC WALL VIEW AT KUTTIPURAM SIDE

    
    
DECK SLAB REINFORCEMENT IN P6-P7

      
 

 

 

 

 

 

 

 