Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
PCC for RAFT MOYAN SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PCC for RAFT PALAKKAD SCHOOL SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
RAFT PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
RAFT MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER CAP PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
PIER CAP MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
RE/R WALL PALAKKAD SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
RE/R WALL MOYAN SCHOOL SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
BEAM/SLAB Staging Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB Bar bending and Fixing Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB Shuttering and Concreting Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
o |
|
|
BEAM/SLAB Staging Moyan schoolSIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB Bar bending and Fixing Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB Shuttering and Concreting Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB PALAKKAD SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB MOYAN SCHOOL SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
BEAM/SLAB RAILWAY SPAN |
7 |
3 |
4 |
0 |
0 |
0 |
0 |
0 |
|
|
HR/FP/KERB Pkd SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
HR/FP/KERB Moyen's SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
HR/FP/KERB RAILWAY SPAN |
100% |
42% |
58% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
BC/PAINTING |
100% |
50% |
50% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|