   Weekly progress report as on 12.10.2012
    
ROB at Parappanangady    
Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
RE Wall panel casting ( total600 nos) Completed Errection completed.
Slab calicut side  (total 10 nos ) Completed  10 nos, adjacent span completed.
slab NH side ( 11 nos) Completed  11 nos,adjacent span completed.
Retaining wall NH side completed completed
Retaining wall calicut side completed  completed
Dirt wall AP2 concreting  completed Done 100%
Dirt wall AP1 concreting  completed Done 100%
Handrail casting completed 1400 nos completed.
Adjacent span RP1-P9 completed completed.
Adjacent span RP4-P10 completed completed.
Handrail fixing completed  completed..adj; span pending
NH side RE panel errection completed 100% completed.
RE wall work calicut side. completed 100% completed.
expansion joint  completed completed.adj; span NH side balance.
painting-slab completed Existing structures completed (adjacent span balance ).
RAILWAY PORTION    
Pilling work  Completed piling completed.
 RP1 In progress pier ,piercap completed.
 RP2 In progress pier & piercap completed.
 RP3 In progress pier & piercap completed.
 RP4 In progress pier &piercap completed.
 
Back
 
    
TEMPERORY STAGING WORK IN RP3.

    
    
MASTIC WORK IN PROGRESS.

    
    
FOUNDATION CONCRETED IN RP2.

    
    
EXPANSION JOINT WORK IN P10.

    
 
 
 

 

 

 

 

 

 

 