   Weekly progress as on 12-10-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 1 1 0 0   Completed
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 10.00%   Diversion work in progress.Excavation for RW started.
14 RE/R WALL Thamarassery side SIDE 100% 50% 50% 0 10.00% 0.00% 0.1 10.00% 5 Delayed due to WATERLOGGING.Excavation started.
15 RE/R WALL NH SIDE 100% 95% 5% 0 5.00% 0.00% 0.05 0.00% 5 RW completed. Only hand rail work balance
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0   Completed
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   Completed
18 BEAM/SLAB NH SIDE 11 9 2 0 0 0 0 0   staging&steel work for super structure between P8-P9 in progress
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 0.00% 0.00% 0 10.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 60% 40% 0 20.00% 10.00% 0.1 20.00%   Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 60% 100% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   10-06-12 10-07-12 10-08-12 10-09-12 10-10-12 10-11-12 10-12-12    
  Nof labours   45 28 48 44 44 42 40    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 60                
  Fine Aggreagate(m3) 50 60                
  Cement(bag) 750 900                
  Steel(MT) 40 50                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STAGING IN PROGRESS P8-P9

    
    
SIDE WALL CONCRETING NH SIDE

    
    
PIER CAP CONCRETING P(9)

    
    
PAINTING STARTED FOR RAILWAY SPAN

    
 
    
P9 PIER CAP

    
    
LONG VIEW FROM T JUNCTION

    
    
HAND RAIL FIXING IN PROGRESS AP3 SIDE

    
 
    
DIRT WALL STEEL WORK IN PROGRESS AP2 SIDE

      
 

 

 

 

 

 

 

 