Progress Report For Devdhar ROB for the week ending on 05-10-2012
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE  CALICUT  SIDE 48 48 0 1 0 0 1 0
2 PILE THIRUR SIDE 24 24 0 11 0 0 11 0
3 PILE CAP CALICUT  SIDE 12 12 0 1 0 0 1 0
4 PILE CAP  THIRURSIDE 6 6 0 5 0 0 5 0
5 PIER CALICUT SIDE 12 12 0 1 0 0 1 0
6 PIER THIRUR SIDE 6 6 0 1 0 0 1 0
7 PIER CAPCALICUT   SIDE 12 12 0 2 0 0 2 0
8 PIER CAP THIRUR SIDE 6 6 0 3 0 0 3 0
9 RETAINING WALL WALL CALICUT   SIDE 100% 65.00% 35% 0 0.00% 0.00% 30.00% 0.00%
10 RETAINING WALL THIRUR SIDE 100% 65% 35% 0 10.00% 10.00% 70.00% 10.00%
11 BEAM CALICUT   SIDE 12 10 2 0 1 1 7 0
12 SLAB CALICUT SIDE 12 10 2   1 0 9 1
13 BEAM THIRUR SIDE 6 4 2 0 1 1 8 0
14 SLAB TIRUR SIDE 6 4 2 0 0 0 1 0
15 HR/FP/KERB CALICUT   SIDE 100% 35% 65% 0 5.00% 5.00% 5.00% 5.00%
16 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 5.00% 0.00% 5.00%
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
18 Culvert calicut side 100% 0 100% 0 0.00% 0.00% 0.00% 5.00%
 