   Weekly Progress Report as on 05.10.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 15 6 - 0 0 0 1
6 Hand Rails 21 6 15   2 2 0 2
7 Expansion Joint 21 4 17   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 29.09.12 01.10.12 02.10.12 03.10.12 04.10.12 05.10.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 75 74 78 78 76 75      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 25 m3 28 m3              
Coarse Aggregate 28 m3 30 m3              
Cement 150 bags 300 bags              
Steel 24 MT 30 MT              
 
Back
 
    
BEAM REINFORCEMENT WORKS IN P6-P7

    
    
SLAB SHUTTERING WORKS IN P6-P7

    
    
VIEW AT KUTTIPURAM SIDE

    
    
VIEW OF P6-P7

    
 
 
 

 

 

 

 

 

 

 