Progress Report For Koilandy ROB for the week ending on 05-10-2012 |
|
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE Muthambi side |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
2 |
PILE Thamarassery side |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
3 |
PILE NH SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
4 |
PILE CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
5 |
PILE CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
6 |
PILE CAP NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
7 |
PIER Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
8 |
PIER Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
9 |
PIER NH SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
10 |
PIER CAP Muthambi SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
11 |
PIER CAP Thamarassery SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
Completed |
12 |
PIER CAP NH SIDE |
10 |
9 |
1 |
0 |
1 |
0 |
1 |
1 |
WORK IN PROGRESS |
13 |
RE/R WALL Muthambi side |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Diversion work in progress |
14 |
RE/R WALL Thamarassery side SIDE |
100% |
50% |
50% |
0 |
10.00% |
0.00% |
0.1 |
10.00% |
Delayed due to WATERLOGGING |
15 |
RE/R WALL NH SIDE |
100% |
95% |
5% |
0 |
5.00% |
0.00% |
0.05 |
0.00% |
RW completed. Only hand rail work balance |
16 |
BEAM/SLAB Muthambi SIDE |
8 |
8 |
0 |
0 |
0 |
0 |
0 |
0 |
|
17 |
BEAM/SLAB Thamarassery SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
18 |
BEAM/SLAB NH SIDE |
11 |
9 |
2 |
0 |
0 |
0 |
0 |
0 |
steel work for super structure between P8-P9 in progress |
19 |
HR/FP/KERB Muthambi SIDE |
100% |
50% |
50% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Kerb casting&Hand rail fixing in progress |
20 |
HR/FP/KERB thamarassery SIDE |
100% |
50% |
50% |
0 |
20.00% |
10.00% |
0.1 |
20.00% |
Kerb casting&Hand rail fixing in progress |
21 |
HR/FP/KERB NH SIDE |
100% |
60% |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
Kerb casting&Hand rail fixing in progress |
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0 |
0.00% |
|
23 |
Utility shifting |
|
|
|
|
|
|
0 |
|
KSEB utility shifting started. Shifted 1 post |