Progress Report For Koilandy ROB for the week ending on 05-10-2012  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0 Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0 Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0 Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0 Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0 Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0 Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0 Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0 Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0 Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0 Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0 Completed
12 PIER CAP NH SIDE 10 9 1 0 1 0 1 1 WORK IN PROGRESS
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00% Diversion work in progress
14 RE/R WALL Thamarassery side SIDE 100% 50% 50% 0 10.00% 0.00% 0.1 10.00% Delayed due to WATERLOGGING
15 RE/R WALL NH SIDE 100% 95% 5% 0 5.00% 0.00% 0.05 0.00% RW completed. Only hand rail work balance
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0  
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0  
18 BEAM/SLAB NH SIDE 11 9 2 0 0 0 0 0 steel work for super structure between P8-P9 in progress
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 0.00% 0.00% 0 0.00% Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 50% 50% 0 20.00% 10.00% 0.1 20.00% Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 60% 100% 0 0.00% 0.00% 0 0.00% Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%  
23 Utility shifting             0   KSEB utility shifting started. Shifted 1 post
 
Back
 
    
TOP VIEW OF PIER CAP P9(T JUNCTION)

    
    
RW WORK IN PROGRESS AT NH SIDE

    
    
LONG VIEW FROM NH SIDE

    
    
KERB AND HAND RAIL WORK IN PROGRESS P21-P22

    
 
    
RW ALONG ROW AT NH SIDE

    
    
TOP VIEW OF PIER CAP P9

    
    
RW ALONG ROW AT NH SIDE.

    
 
    
HAND RAIL FIXING IN PROGRESS.

      
 

 

 

 

 

 

 

 