Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
89% |
11% |
5% |
5.00% |
3.00% |
2.00% |
5.00% |
|
Friction slab complete for 30m at RHS |
10 |
RE/RC WALL PADANNA SIDE |
100% |
55% |
45% |
5% |
5.00% |
0.00% |
5.00% |
5.00% |
|
Excavation 90% complete,Remaining works held up due to high water table level. |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
8 |
1 |
complete except railway adjacent span |
|
|
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
7 |
2 |
0 |
0 |
0 |
0 |
0 |
|
complete except AP2 and P8 |
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
0 |
0 |
0 |
0 |
0 |
|
complete except AP1 and P7 |
15 |
KERB CHERUVATHOOR SIDE |
100% |
80.00% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab and RC Wall portion |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
80% |
20% |
0.00% |
0.00% |
0.00% |
0.00% |
0.00% |
|
RC Wall handrail 100% complete |
18 |
HANDRAIL PADANNA SIDE |
100% |
79% |
21% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
|
RC Wall handrail 100% complete |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
Grinding and finishing works in progress at chr side |
18 |
Others/Miscellaneous |
|
|
|
|
|
|
|
|
|
Drainage works complete for 56 m at chr side,excavation complete for another 21 m. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
AP1 Dirt wall concreted. |
|
|
|
|
|
|
|
|
|
|
|
Drainage works and remaining DR Works for service road planned at chr side. |
|
|
|
|
|
|
|
|
|
|
|
Site cleaning works in progress |
19 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
20 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
29-09-12 |
30-09-12 |
01-10-12 |
02-10-12 |
03-10-12 |
04-10-12 |
05-10-12 |
|
|
|
|
No of labours |
19 |
21 |
19 |
16 |
16 |
16 |
16 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
450 |
30 |
shortage |
|
|
|
|
|
|
|
Steel(MT) |
2 |
1 |
shortage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
BSNL |
shifting complete at Padanna side RE Panel area. |
|
|
|
|
|
|
|
KSEB |
|
electric post infront of unity hospital and lines over RC Wall area at Padanna side need to be shifted urgently,currently not affecting the works.AXE and AE visited the site on 27-09-12. |
|
|
|
|
|
|
|
KWA |
currently can be managed at site |
|
|
|
|
|
|
|
Others |
|
|
|
|
|
|
|
|
|
|