Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053873
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 05.10.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 89% 11% 5% 5.00% 3.00% 2.00% 5.00%   Friction slab complete for 30m at RHS
10 RE/RC  WALL PADANNA SIDE 100% 55% 45% 5% 5.00% 0.00% 5.00% 5.00%   Excavation 90% complete,Remaining works held up due to high water table level.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 80.00% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 80% 20% 0.00% 0.00% 0.00% 0.00% 0.00%   RC Wall handrail 100% complete
18 HANDRAIL PADANNA SIDE 100% 79% 21% 0% 0.00% 0.00% 0.00% 0.00%   RC Wall handrail 100% complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at chr side
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side,excavation complete for another 21 m.
                       
                      AP1 Dirt wall concreted.
                      Drainage works and remaining DR Works for service road planned  at chr side.
                      Site cleaning works in progress
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 29-09-12 30-09-12 01-10-12 02-10-12 03-10-12 04-10-12 05-10-12      
  No of labours 19 21 19 16 16 16 16      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 450 30 shortage            
  Steel(MT) 2 1 shortage            
                       
                       
  Utility shifting              
  Utilities to be shifted Status Remarks                
  BSNL shifting complete at Padanna side RE Panel area.            
  KSEB   electric post infront of unity hospital and lines over RC Wall area at Padanna side need to be shifted urgently,currently not affecting the works.AXE and AE visited the site on 27-09-12.            
  KWA currently can be managed at site             
  Others                    
 
Back
 
    
HANDRAIL FINISHING WORKS

    
    
FRICTION SLAB CONCRETE

    
    
CHR APPROACH AREA

    
    
VIEW OF CHR SIDE

    
 
 
 

 

 

 

 

 

 

 

Untitled Document