   25.09.2010
    

 

ROB Koratty
Description
 
Completed/ Progress
 
Remarks
 
Approval of GAD by railways (Railway Portion)
 
Approved
 
Approved on 1-5-10
 
Design and Drawing
 
Submitted
 
Approval pending with Railways
 
Retaining wall concreting
 
In progress
 
 
RE Wall work near Under Pass
 
 
In progress  
PCC & RCC for drain near approach road
 
In progress  
 