   weekly progress report as on 05/10/2012
    

 

All aproach spans completed.

Re wall on Pulikakadavu side 100% completed

Re wall on NH side 93% completed

CRS sanction obtained  for the construction of railway  span and the  work will be started after getting caution from railways.

 
Back
 
    
TEMPERORY STAGING WORK AT NH SIDE

    
    
TEMPERORY STAGING FOUNDATION WORK

    
    
REINFORCEMENT FOR THE FOOTING AT NH SIDE

    
    
CURING OF STAGING FOUNDATION

    
 
    
CURING IN PROGRESS

    
    
CENTRE SPAN WORK IN PROGRESS

      
 

 

 

 

 

 

 

 