Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8052993
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 28.09.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 85% 15% 10% 10.00% 4.00% 6.00% 5.00%   PCC complete for friction slab at RHS,reinforcement works IP
10 RE/RC  WALL PADANNA SIDE 100% 50% 50% 30% 5.00% 5.00% 0.00% 5.00%   Well inside bsnl compound has been demolished,Excavation 30% complete,water logging causes delay.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 80.00% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 76% 24% 0.00% 4.00% 4.00% 0.00% 0.00%   RC Wall handrail 100% complete
18 HANDRAIL PADANNA SIDE 100% 64% 36% 0% 15.00% 15.00% 0.00% 0.00%   RC Wall handrail 100% complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at chr side
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side,excavation complete for another 21 m.
                      Bar bending 80% complete for friction slab at chr side.
                      AP1 Dirt wall concreted.
                      Drainage works and remaining DR Works for service road planned  at chr side.
                      Site cleaning works in progress
19 Deck Slab                    
20 Utility shifting                    
                       
 
Back
 
    
CHR SIDE RE PANEL

    
    
REINFORCEMENT IP FOR FRICTION SLAB

    
    
VIEW OF PADANNA SIDE

    
    
VIEW OF CHR SIDE

    
 
 
 

 

 

 

 

 

 

 

Untitled Document