   Weekly Progress Report as on 28.09.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 15 6 - 0 0 0 Beam Reinforcement
6 Hand Rails 21 4 17   2 2 0 2
7 Expansion Joint 21 2 19   2 2 0 2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 22.09.12 24.09.12 25.09.12 26.09.12 27.09.12 28.09.12      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 70 70 75 75 78 80      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 23 m3 28 m3              
Coarse Aggregate 22 m3 25 m3              
Cement 180 bags 300 bags              
Steel 28 MT 35 MT              
 