   weekly progress report as on 28/09/2012
    

KORATTY ROB

PROGRESS REPORT (upto September  28th  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

 

1.Concreting of the Dirt wall completed in the NH side

2.Foundation work and concreting for the pedestal for the temperory staging between upline and downline

 

CAUTION FOR THE TEMPERORY STAGING WORKS TILL 30-09-2012

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

22-9-2012

12

24-9-2012

11

25-9-2012

11

26-9-2012

12

27-9-2012

12

28-9-2012

11

 

 

 

 

 

 

 

             

 

 

 
Back
 
    
SHUTTERING WORK OF THE PEDESTAL COLUMN

    
    
FOUNDATION WORK IN THE UPLINE PORTION

      
 

 

 

 

 

 

 

 