   Weekly progress report as on 21.09.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 10.00% 5.00% 15.00% 10.00%   work in progress,friction slab works planned next week.
10 RE/RC  WALL PADANNA SIDE 100% 50% 50% 30% 0.00% 0.00% 0.00% 5.00%   Well inside bsnl compound has been demolished,Site clearing works started for RE Panel works.
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 80.00% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 61% 39% 0.00% 10.00% 15.00% 0.00% 4.00%   RC Wall handrail 80% complete
18 HANDRAIL PADANNA SIDE 100% 64% 36% 0% 0.00% 0.00% 0.00% 15.00%   RC Wall handrail planned
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at chr side
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side.
                      Bar bending 80% complete for friction slab at chr side.
                      AP1 Dirt wall concreted.
                      Drainage works and remaining DR Works for service road planned  at chr side.
                      Site cleaning works in progress
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 15-09-2012 16-09-2012 17-09-2012 18-09-2012 19-09-2012 20-09-2012 21-09-2012      
  No of labours 1 22 26 26 26 25 25      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 70 250              
  Steel(MT) 1 5              
                       
 