   Weekly Progress Report as on 21.09.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 20.09.12 Balance  work up to 20.09.12 Cumulative delay in Qty up to 20.09.12 Work  planned  during the week  Actual work done during the week delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 31 0 0 0 0 0 0 completed KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.Rig erected at P9
2 PILE Palarivattom side(railway portion) 6 6 0 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 42 0 0 0 0 0 0 completed Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 6 0 0 0 0 0 0 RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned.Piling resumed on 29.02.12. Piling held up pending approval  fron RLY. Piling commenced on 06.06.12.
5 PILE CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattom side(railway portion) 1 0 1 0 0 0 0 0  
7 PILE CAP vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1,  P2, P4, P3, A1, P5,P6, P7,P8
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed A2, P15, P14, P13,  P12,  P11, P10, P9 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, P4, A1,P5,P6,P7, P8
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0    
13 PIER  CAP Palarivattom side(Approach portion) 8 8 0 0 0 0 0 0 completed P15, P14, A2, P13, P12, P11, P10, P9
14 PIER  CAP Vytila side(Approach portion) 9 9 0 0 0 0 0 0 completed P1, P2, P3, A1,P4,P5,P6,P7, P8
15 GIRDER Palarivattom side(Approach portion) 8 7 1 0 0 0 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10, P12 P11, P10P9
16 GIRDER Vytila side(Approach portion) 9 7 2 0 0 0 0 0   P1P2,  A1P1, P2P3, P3P4, P5P6, P6P7, P4P5
17 DECK SLAB Palarivattom side(Approach portion) 8 6 2 0 0 0 0 0   A2 P15, P15 P14, P14 P13,  P13 P12, P11P10, P12 P11
18 DECK SLABVytila side(Approach portion) 9 7 2 0 0 0 0 0   P1P2,A1P1, P2P3, P3P4, P4P5, P5P6, P6P7
19 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
20 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
21 RE WALL PANEL CASTING 351 351 0 0 0 0 0 0    
20 RE WALL PCC Palarivattom 95 95 0 0 0 0 0 0   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.
21 RE WALL Panel erection Palarivattom 100% 70% 0.3 0.3 0% 0% 30% 0%   Rerouting of water connection to photostat shop  by KWA to the completed on 24.03.12. on 24.04.12 the entire RE Wall area was cleared for excavation.Panel erection commenced on 15.05.12. No work due to rain. Work resumed on 30.07.12. work held up again.
21 RE WALL Earth filling PALARIVATTOM 100% 27% 0.73 73 0% 2% 73% 0%   Earth filling not done due to rain.Work resumed on 30.07.12. 
22 Rly Pile Load test 1 1 0 0 1 1 0 0   completed
 