   weekly progress report as on 21/09/2012
    

KORATTY ROB

PROGRESS REPORT (upto September  21st  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

 

1.Shuttering work for the Dirt wall in NH side

2.Trenching work for the Msand filling and PCC Laying for the temperory staging of the central span

3.Painting works of the deck slab in progress

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

15-9-2012

5

17-9-2012

5

18-9-2012

6

19-9-2012

7

20-9-2012

7

21-9-2012

6

 

 

 

 

 

 

 

             

 

 

 
Back
 
    
TRENCHING WORK FOR THE M SAND FILLING AND PCC LAYING FOR THE STAGING FOUNDATION

    
    
PCC FOR THE FOUNDATION OF THE TEMPERORY STAGING FOR THE CENTRAL SPAN

      
 

 

 

 

 

 

 

 