KORATTY ROB
PROGRESS REPORT (upto September 21st 2012)
RAILWAY PORTION
Total scope: 4 Locations
LOCATIONS:P1,P7 ,P8,P2
P1,P7 –N.H side
P8,P2-Pulikkakadavu side.
Total Piles: 18
No of PILES IN EACH LOCATION
P1 location: 4
P7 location:5
P8 location:5
P2 location:4
WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION
P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.
P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam
P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam
P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.
Approach portion at N.H side completed 90%
WORK COMPLETED AT PULIKKAKADAVU SIDE
All deck slab concreting completed at pulikkakadavu side.
Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.
WORKS BALANCE
P1-P7 superstructure (RCC structure)
P7-P8 superstructure( CENTRAL SPAN)
P8-P2 superstructure (RCC structure)
Awaiting the sanction from the railways for the superstructure drawing.
WORK COMPLETED THIS WEEK
1.Shuttering work for the Dirt wall in NH side
2.Trenching work for the Msand filling and PCC Laying for the temperory staging of the central span
3.Painting works of the deck slab in progress
LABOUR REPORT
DATE
|
NO: OF LABOURS
|
15-9-2012
|
5
|
17-9-2012
|
5
|
18-9-2012
|
6
|
19-9-2012
|
7
|
20-9-2012
|
7
|
21-9-2012
|
6
|
|
|
|