Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887305
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly report as on 14-09-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 1 0 1 1    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%   Diversion work in progress
14 RE/R WALL Thamarassery side SIDE 100% 50% 50% 0 10.00% 0.00% 0.1 10.00% 5 Delayed due to rain
15 RE/R WALL NH SIDE 100% 90% 65% 0 10.00% 0.00% 0.1 10.00% 3  Side wall final lift (Haunch) work in progress .
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0    
18 BEAM/SLAB NH SIDE 11 8 3 0 0 0 0 1   shuttering work for girder between P6-RP1 in progress
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 20% 80% 0 20.00% 10.00% 0.1 20.00%   Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 60% 100% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   09-08-12 09-09-12 09-10-12 09-11-12 09-12-12 13/9/2012 14/9/2012    
  Nof labours   35 20 40 45 45 40 42    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 75                
  Fine Aggreagate(m3) 50 75                
  Cement(bag) 750 900                
  Steel(MT) 30 50                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STEEL WORK FOR DECK SLAB P15-16

    
    
HAND RAIL WORK IN PROGRESS

    
    
DECK SLAB CONCRETING P18-19

    
    
DECK SLAB CONCRETING P15-16

    
 
    
CURVED PORTION P15-16

      
 

 

 

 

 

 

 

 

Untitled Document