Details of work done between 16th to 21st Nov 2009
Work Planned upto 21/11/2009 |
Completed/Progress |
Delay |
Hand rail fixing |
In progress, Malampuzha
side completed
|
|
Retaining wall excavation |
In progress |
|
Retaining wall reinforcement |
Bending in progress |
|
Toll booth plinth beam |
Completed |
|
Lifting work |
Cleaning in progress |
|
|