   Weekly Progress Report as on 14-09-2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 0 - - - - -
5 Deck Slab 21 13 8 - - 0 0 1
6 Hand Rails 21 3 18   1 1 0 1
7 Expansion Joint 21 0 21   2 2   2
8 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 08.09.12 10.09.12 11.09.12 12.09.12 13.09.12 14.09.12      
Climate Pleasant Rain Pleasant Rain Pleasant Pleasant      
No. of labours 75 76 75 74 72 75      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 24 m3 30 m3              
Coarse Aggregate 25 m3 30 m3              
Cement 200 bags 400 bags              
Steel 28 MT 33 MT              
 
Back
 
    
SLAB REINFORCEMENT IN P5-P6

    
    
BEAM REINFORCEMENT IN P3-P4

    
    
BEAM SHUTTERING COMPLETED IN P3-P4

      
 

 

 

 

 

 

 

 