   Weekly Progress Report as on 14.09.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 5.00% 0.00% 20.00% 10.00%   rain still prevailing,red earth stacking started.
10 RE/RC  WALL PADANNA SIDE 100% 50% 50% 30% 0.00% 0.00% 0.00% 0.00%   Land not available for RE Panel works,cable shifting works 70% complete
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 7 2 0 0 0 0 0   complete except AP2 and P8
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   complete except AP1 and P7
15 KERB CHERUVATHOOR  SIDE 100% 80.00% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 61% 39% 0.00% 10.00% 0.00% 10.00% 10.00%   RC Wall handrail planned
18 HANDRAIL PADANNA SIDE 100% 64% 36% 0% 0.00% 0.00% 0.00% 0.00%   AP1-P7 Spans complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   Grinding and finishing works in progress at chr side
18 Others/Miscellaneous                   Drainage works complete for 56 m at chr side.
                      Bar bending 80% complete for friction slab at chr side.
                      AP1 Dirt wall concreted.
                      Drainage works and remaining DR Works for service road planned  at chr side.
                      Site cleaning works in progress
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 08-09-2012 09-09-2012 10-09-2012 11-09-2012 12-09-2012 13-09-2012 14-09-2012      
  No of labours 29 1 29 29 26 20 20      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 100 270              
  Steel(MT) 1 5              
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL  Obstruction at Padanna side RC wall area cleared     BY CONTRACTOR,shifting of cables at RE Panel area padanna side is in progress.            
  KSEB   electric post infront of unity hospital and lines over RC Wall area at Padanna side need to be shifted urgently.            
  KWA currently can be managed at site                   
  Others                    
 
Back
 
    
SITE CLEANING

    
    
SHIFTED CABLES AT BSNL LOCALITY

    
    
RED EARTH ARRIVED AT SITE

    
    
GRINDING WORKS IP

    
 
 
 

 

 

 

 

 

 

 