Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887321
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 07.09.2012
    
Progress Report - ROB-Thirunavaya   -07.09.2012
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week
1 Piles 63 63 - - - - -
2 Pile cap 21 21 - - - - -
3 Pier  21 21 - - - - -
4 PierCap 21 21 - - - - 0
5 Deck Slab 21 12 9 -  staging P5-P6 and P3-P4  staging P5-P6 and P3-P4 0
  Hand Rails 21 3 18   0 0 0
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0%
 
Back
 
    
REINFORCEMENT OF BEAM FOR THE SPAN P5-P6

    
    
STAGING FOR P3-P4

    
    
ROB THIRUNAVAYA KUTTIPURAM SIDE

      
 

 

 

 

 

 

 

 

Untitled Document