Details of work done between 7th to 12th Dec 09.
Work Planned upto 12.12.2009 |
Completed/Progress |
Delay |
Retaining wall reinforcement fixing |
In progress |
|
Retaining wall concreting |
In progress |
|
Toll booth up to slab level |
Completed |
|
Lifting work |
Cleaning in progress |
|
|