   Weekly report as on 07-09-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 1 0 1 1    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%   Diversion work in progress
14 RE/R WALL Thamarassery side SIDE 100% 50% 50% 0 10.00% 0.00% 0.1 10.00% 5  
15 RE/R WALL NH SIDE 100% 85% 65% 0 15.00% 5.00% 0.1 10.00% 5  Side wall final lift (Haunch) work in progress .
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 10 0 0 0 0 0 0   shuttering work for deck between P15-P16 & P18-P19  in progress
18 BEAM/SLAB NH SIDE 11 8 3 0 0 0 0 0    
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 10.00% 0.00% 0.1 0.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 10% 90% 0 15.00% 10.00% 0.05 20.00%   Kerb casting&Hand rail fixing in progress
21 HR/FP/KERB NH SIDE 100% 60% 100% 0 0.00% 0.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   09-01-12 09-02-12 09-03-12 09-04-12 09-05-12 09-06-12 09-07-12    
  Nof labours   42 18 30 38 40 42 40    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 50 75                
  Fine Aggreagate(m3) 50 75                
  Cement(bag) 1000 1700                
  Steel(MT) 40 60                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STAGING DONE FOR PIER CAP P9

    
    
STAGING DONE FOR P6-RP1

    
    
RETAINING WALL HAUNCH AT NH SIDE

    
    
LONG VIEW FROM AP2

    
 
    
DIVERSION WORK IN PROGRESS AT AP2

      
 

 

 

 

 

 

 

 