   weekly progress report as on 07/09/2012
    

KORATTY ROB

PROGRESS REPORT (upto September  07th  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

 

1.Outer kerb shuttering and reinforcement work in NH side

2.Outer kerb concreting at the NH side

 

 

 

 

 

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

01-9-2012

3

03-9-2012

4

04-9-2012

4

05-9-2012

5

06-9-2012

4

07-9-2012

4

 

 

 

 

 

 

 

             

 

 

 
Back
 
    
STAGING WORK OF THE APPROACH SLAB CONCRETING AT NH SIDE

    
    
CONCRETING OF THE OUTER KERB AT NH SIDE

      
 

 

 

 

 

 

 

 