   Weekly progress Report as on 31.08.12
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 21 - - - - 0 0
5 Deck Slab 21 12 9 - 1 1 0  staging P5-P6 and P3-P4
  Hand Rails 21 3 18   1 0 1 1
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 25.08.12 27.08.12 28.08.12 29.08.12 30.08.12 31.08.12      
Climate Pleasant Rain Rain Rain Rain Rain      
No. of labours 65 57 57 50 57 57      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 25 m3              
Coarse Aggregate 20 m3 25 m3              
Cement 100bags 150 bags              
Steel 28 MT 33 MT              
 
Back
 
    
KUTTIPURAM SIDE

    
    
KUTTIPURAM AP1 SIDE

    
    
STAGING P3-P4

    
    
STAGING P5-P6

    
 
 
 

 

 

 

 

 

 

 