Prevoius Weekly Reports

   Weekly progress report as on 31.08.2012
    

KORATTY ROB

PROGRESS REPORT (upto August  24th  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

 

1.Outer kerb concreting in progress after the reinforcement and shuttering works

2.Approach slab concreting in progress

 

 

 

 

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

18-8-2012

5

20-8-2012

4

21-8-2012

5

22-8-2012

5

23-8-2012

4

24-8-2012

6

 

 

 

 

 

 

 

             

 

 

 
Back
 
    
SHUTTERING WORKS FOR THE OUTER KERB

    
    
REINFORCEMENT WORKS FOR THE OUTER KERB AT NH SIDE

    
    
APPROACH SLAB PCC IN PROGRESS

      
 

 

 

 

 

 

 

 