Details of work done done between 28th Dec 2009 and 2 jan 2010
Work Planned upto 02.01.2010 |
Completed/Progress |
Delay |
Retaining wall reinforcement fixing |
In progress |
|
Retaining wall concreting |
In progress |
|
Toll booth concreting slab |
Completed |
|
Lifting work - one spam |
In progress |
|
Chipping of pedestals |
In progress |
|
|