   weekly progress report as on 24/08/2012
    

KORATTY ROB

PROGRESS REPORT (upto August  17th  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:5 pile concreting completed,pile cap,trestle column,trestle beam

 

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 90%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

 

 

Awaiting the sanction from the railways for the superstructure drawing.

WORK COMPLETED THIS WEEK

 

1.Outer kerb concreting completed in NH side

 

 

 

 

 

 

 

 

 

LABOUR REPORT

DATE

NO: OF LABOURS

11-8-2012

5

130-8-2012

5

14-8-2012

5

15-8-2012

5

16-8-2012

6

17-8-2012

6

 

 

 

 

 

 

 

              

 

 

 
Back
 
    
REINFORCEMENT WORK

    
    
REINFORCEMENT WORK FOR THE OUTER KERB AT NH SIDE

    
    
OUTER KERB CONCRETING IN NH SIDE

      
 

 

 

 

 

 

 

 