Prevoius Weekly Reports

   Weekly progress graph as on 24.08.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 20 1 - 1 1 0 0
5 Deck Slab 21 11 10 - 1 1 0 1
  Hand Rails 21 3 18   1 0 1 1
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 18.08.12 20.08.12 21.08.12 22.08.12 23.08.12 24.08.12      
Climate Pleasant Rain Pleasant Pleasant Pleasant Pleasant      
No. of labours 65 63 63 65 65 65      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 24 m3 30 m3              
Coarse Aggregate 25 m3 30 m3              
Cement 130bags 200bags              
Steel 28 MT 33 MT              
 
Back
 
    
BEAM WORKS IN P2-P3

    
    
PIER CAP REINFORCEMENT P10

    
    
SHUTTERING WORKS IN P2-P3

    
    
SLAB WORKS IN P4-P5

    
 
 
 

 

 

 

 

 

 

 