Prevoius Weekly Reports

   Weekly progress as on 17-08-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 1    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 45% 55% 0 10.00% 5.00% 0.05 10.00% 5  Side wall final lift work in progress at one side.
15 RE/R WALL NH SIDE 100% 85% 65% 0 15.00% 0.00% 0.15 15.00% 5 Raft& Side wall 1st & 2nd lift done .Dirt wall completed.Final lift work in progress
16 BEAM/SLAB Muthambi SIDE 8 8 0 0 0 0 0 0    
17 BEAM/SLAB Thamarassery SIDE 10 9 1 0 1 1 0 0   shuttering work for deck between P15-P16 & P18-P19  in progress
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 1   Staging completed for  P17-P18
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 0.00% 0.00% 0 10.00%   Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 15.00% 0.00% 0.15 15.00%    
21 HR/FP/KERB NH SIDE 100% 45% 100% 0 10.00% 10.00% 0 0.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   08-11-12 08-12-12 13/8/2012 14/8/2012 15/8/2012 16/8/2012 17/8/2012    
  Nof labours   38 23 40 45 0 42 20    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 70 100                
  Fine Aggreagate(m3) 70 100                
  Cement(bag) 800 1200                
  Steel(MT) 40 70                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
STAGING IN PROGRESS P17-18

    
    
LONG VIEW FROM T JUNCTION

    
    
STAGING AT T JUNCTION

    
    
DECK SLAB P16-17 IN PROGRESS

    
 
    
DECK SLAB CONCRETING P16-17

      
 

 

 

 

 

 

 

 

Untitled Document