   18.09.2010
    

ROB at Bakel

Description Completed / Progress Remarks
Span on Kasargod side    
Hand rail casting Completed Slow progress due to heavy rains
Span on Kannur Side    
Concreting of beams Completed  
Shuttering work for Slab Progress Road Blocked on 24.07.2010
 
Back
 
    
FINAL SLAB SHUTTERING ROB AT BAKEL

    
    
BAR BENDING ROB AT BAKEL

    
    
2 FINAL SLAB SHUTTERING ROB AT BAKEL

    
    
1BAR BENDING ROB AT BAKEL

    
 
    
1 FINAL SLAB SHUTTERING ROB AT BAKEL

      
 

 

 

 

 

 

 

 