   Weekly Progress Report as on 17.08.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week    
1 Piles 63 63 - - - - - -    
2 Pile cap 21 21 - - - - - -    
3 Pier  21 21 - - - - - -    
4 PierCap 21 19 2 - 1 1 0 1    
5 Deck Slab 21 11 10 - 0 0 0 Shuttering works P2-P3 & P4-P5
  Hand Rails 21 3 18   1 1 0 1    
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%    
                       
Date 11.08.12 13.08.12 14.08.12 15.08.12 16.08.12 17.08.12          
Climate Pleasant Rain Rain Rain Pleasant Rain          
No. of labours 55 55 57 40 57 58          
                       
                       
Availability of Materials                    
                       
Material Required Available                  
Fine aggregate 20 m3 28 m3                  
Coarse Aggregate 28 m3 33 m3                  
Cement 200bags 400bags                  
Steel 28 MT 35 MT                  
 
Back
 
    
BEAM REINFORCEMENT WORKS IN P4-P5

    
    
PIER CAP WORKS IN P10

    
    
PIER CAP REINFORCEMENT IN P9

    
    
BEAM REINFORCEMENT WORKS IN P2-P3

    
 
 
 

 

 

 

 

 

 

 