Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053062
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress Report as on 10.08.12
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 0.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 47% 53% 30% 3.00% 3.00% 0.00% 0.00%   Land not available for RE Panel works
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 8 1 complete except railway adjacent span    
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 1 0 1 1    
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   P1-P6 locations complete
15 KERB CHERUVATHOOR  SIDE 100% 72.00% 28% 0 8.00% 8.00% 0.00% 0.00%   complete for slab and RC Wall portion
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab and RC Wall portion
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 12.50% 8.00% 0.00% 8.00% 8.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 64% 36% 0% 0.00% 0.00% 0.00% 0.00%   AP1-P7 Spans complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 56 m at chr side.
                      Site cleaning works planned
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 04-08-2012 05-08-2012 06-08-2012 07-08-2012 08-08-2012 09-08-2012 10-08-2012      
  No of labours 28 28 28 28 28 28 28      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 100 600              
  Steel(MT) 2 8              
                       
 
Back
 
    
RC WALL PADANNA SIDE

    
    
RC WALL KERB CONCRETE IP

    
    
HEAVY RAINS AFFECTED CHR SIDE RE PANEL WORKS

    
    
HANDRAIL HORIZ. CASTING IP

    
 
 
 

 

 

 

 

 

 

 

Untitled Document