Prevoius Weekly Reports

   Weekly report as per 10-08-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 1 0 1 0    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 45% 55% 0 10.00% 0.00% 0.1 10.00% 5  Side wall final lift work in progress at one side.
15 RE/R WALL NH SIDE 100% 80% 65% 0 20.00% 5.00% 0.15 15.00% 5 Raft& Side wall 1st & 2nd lift done .Final lift work in progress
16 BEAM/SLAB Muthambi SIDE 8 7 1 0 1 1 0 0   shuttering work for deck between P15-P16 & P16-P17  in progress.Girder P18-19 ready for concrete
17 BEAM/SLAB Thamarassery SIDE 10 9 1 0 1 0 1 1    
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0    
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 25.00% 10.00% 0.15     Kerb casting&Hand rail fixing in progress
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 15.00%    
21 HR/FP/KERB NH SIDE 100% 30% 100% 0 25.00% 15.00% 0.1 10.00%   Kerb casting&Hand rail fixing in progress
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   04-08-12 05-08-12 06-08-12 07-08-12 08-08-12 09-08-12 10-08-12    
  Nof labours   52 20 45 25 50 52 22    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 75 100                
  Fine Aggreagate(m3) 60 100                
  Cement(bag) 1200 1850                
  Steel(MT) 50 75                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
T JUNCTION

    
    
SHUTTERING IN PROGRESS P18-19

    
    
SHUTTERING IN PROGRESS P16-17

    
    
SHUTTERING IN FINAL STAGE P16-17

    
 
    
RETAINING WALL IN FINAL STAGE AT NH SIDE

    
    
LONG VIEW FROM NH SIDE

      
 

 

 

 

 

 

 

 