Prevoius Weekly Reports

   Weekly progress report as on 03-08-2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 27 0 0 0 0 0 0   Completed
2 PILE Thamarassery side 33 33 0 0 0 0 0 0   Completed
3 PILE NH SIDE 33 33 0 0 0 0 0 0   Completed
4 PILE CAP Muthambi SIDE 9 9 0 0 0 0 0 0   Completed
5 PILE CAP Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
6 PILE CAP NH SIDE 10 10 0 0 0 0 0 0   Completed
7 PIER Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
8 PIER Thamarassery SIDE 11 11 0 0 0 0 0 0   Completed
9 PIER NH SIDE 10 10 0 0 0 0 0 0   Completed
10 PIER CAP Muthambi  SIDE 9 9 0 0 0 0 0 0   Completed
11 PIER CAP Thamarassery SIDE 11 10 1 0 1 1 0 0   Completed
12 PIER CAP NH SIDE 10 9 1 0 0 0 0 1    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 45% 55% 0 10.00% 0.00% 0.1 10.00% 5 Raft& Side wall 2nd lift work in progress at one side.
15 RE/R WALL NH SIDE 100% 75% 65% 0 25.00% 5.00% 0.2 25.00% 5 Raft& Side wall 1st lift done .2nd lift work in progress
16 BEAM/SLAB Muthambi SIDE 8 7 1 0 1 0 1 1   shuttering work for deck between P15-P16 & for girder P16-P17 & P18-P19 in progress.
17 BEAM/SLAB Thamarassery SIDE 10 9 1 0 0 0 0 1    
18 BEAM/SLAB NH SIDE 11 7 4 0 0 0 0 0    
19 HR/FP/KERB Muthambi SIDE 100% 50% 50% 0 25.00% 10.00% 0.15     Kerb casting&Hand rail fixing started
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 10.00%    
21 HR/FP/KERB NH SIDE 100% 10% 100% 0 25.00% 20.00% 0.05 25.00%   Kerb casting&Hand rail fixing started
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post
                       
                       
                       
  Availbility of Men                     
  Date   28/7/2012 29/7/2012 30/7/2012 31/7/2012 08-01-12 08-02-12 08-03-12    
  Nof labours   42 27 53 52 55 0 55    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 60 90                
  Fine Aggreagate(m3) 60 90                
  Cement(bag) 1000 1400                
  Steel(MT) 40 100                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL                    
  KSEB                    
  KWA                    
  Others                    
 
Back
 
    
Y JUNCTION WORK IN PROGRESS

    
    
WORK IN PROGRESS P16-P17

    
    
STEEL WORK IN PROGRESS P18-P19

    
    
LONG VIEW FROM AP2 SIDE

    
 
    
DECK SLAB CONCRETING P7-P8

      
 

 

 

 

 

 

 

 

Untitled Document