   weekly progress report as on 03/08/2012
    
PROGRESS OF ROB and ROAD  WORK AS ON 03-08-2012.
  Description Completed/ Progress Remarks
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed Errection completed.
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )adjacent span in progress.
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side completed completed
  Retaining wall calicut side completed  completed
  Dirt wall AP2 concreting  completed Done 100%
  Dirt wall AP1 concreting  completed Done 100%
  Handrail casting completed 1400 nos completed.
  Adjacent span rp1-p9 in progress girder work in progress.
  Handrail fixing completed  completed.
  RAILWAY PORTION    
  Pilling work  Completed piling completed.
   RP1 In progress pier ,piercap completed,rp1-p9 span in progress.
   RP2 In progress pier completed,piercap completed.
   RP3 In progress pier completed.
   RP4 In progress pier completed,piercap completed.
  NH side RE panel erection completed 100% completed.
  RE wall work calicut side. completed 100% completed.
  expansion joint  completed completed.
  painting-slab In progress Existing structures completed.
 
Back
 
    
WBM WORKS APPROACH PORTION.

    
    
RP3 LOCATION.

    
    
SHUTTERING RP1-P9 SPAN.

      
 

 

 

 

 

 

 

 