Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8053606
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 03.08.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 24 Completed    
3 PILE CAP CHERUVATHOOR SIDE 9 9 Completed    
4 PILE CAP  PADANNA SIDE 8 8 Completed    
5 PIER CHERUVATHOOR SIDE 9 9 Completed    
6 PIER PADANNA SIDE 8 8 Completed    
7 PIER CAP CHERUVATHOOR SIDE 9 9 Completed    
8 PIER CAP PADANNA SIDE 8 8 Completed    
9 RE/RC WALL CHERUVATHOOR  SIDE 100% 80% 20% 20% 0.00% 0.00% 20.00% 0.00%   RE Panel works held up due to rain and unavailability of red earth
10 RE/RC  WALL PADANNA SIDE 100% 44% 56% 30% 2.00% 3.00% 0.00% 3.00%   Land not available for RE Panel works
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 7.5 1.5 0.5 0.5 0.5 0 0   P9-P8 deck slab complete
12 BEAM/SLAB PADANNA SIDE 8 7 1 complete except railway adjacent span    
13 EXPANSION JOINT CHERUVATHUR SIDE 9 5 4 0 0 0 0 1    
14 EXPANSION JOINT PADANNA SIDE 8 6 2 0 0 0 0 0   P1-P6 locations complete
15 KERB CHERUVATHOOR  SIDE 100% 72.00% 28% 0 0.00% 0.00% 0.00% 8.00%    
16 KERB PADANNA SIDE 100% 80% 20% 0 0.00% 0.00% 0.00% 0.00%   complete for slab portion
17 HANDRAIL CHERUVATHUR SIDE 100% 45% 55% 12.50% 12.50% 0.00% 12.50% 8.00%   complete for AP2-P10 spans
18 HANDRAIL PADANNA SIDE 100% 64% 36% 0% 0.00% 0.00% 0.00% 0.00%   AP1-P7 Spans complete
17 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
18 Others                   Drainage works complete for 56 m at chr side.
19 Deck Slab                    
20 Utility shifting                    
                       
                       
                       
  Availbility of Men                     
  Date 28-07-2012 29-07-2012 30-07-2012 31-07-2012 01-08-2012 02-08-2012 03-08-2012 ########    
  No of labours 47 28 35 28 35 5 5 24    
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) available                
  Fine Aggreagate(m3) available                
  Cement(bag) 150 100 shortage             
  Steel(MT) 5 15              
                       
 
Back
 
    
VIEW OF PADANNA SIDE

    
    
PADANNA SIDE

    
    
P9-P8 DECK SLAB CONCRETE

    
    
BSNL CABLE SHIFTING STARTED AT PADANNA SIDE RE WALL AREA

    
 
 
 

 

 

 

 

 

 

 

Untitled Document