Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE CHERUVATHOOR SIDE |
27 |
27 |
Completed |
|
|
2 |
PILE PADANNA SIDE |
24 |
24 |
Completed |
|
|
3 |
PILE CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
4 |
PILE CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
5 |
PIER CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
6 |
PIER PADANNA SIDE |
8 |
8 |
Completed |
|
|
7 |
PIER CAP CHERUVATHOOR SIDE |
9 |
9 |
Completed |
|
|
8 |
PIER CAP PADANNA SIDE |
8 |
8 |
Completed |
|
|
9 |
RE/RC WALL CHERUVATHOOR SIDE |
100% |
80% |
20% |
20% |
0.00% |
0.00% |
20.00% |
0.00% |
|
RE Panel works held up due to rain and unavailability of red earth |
10 |
RE/RC WALL PADANNA SIDE |
100% |
44% |
56% |
30% |
2.00% |
3.00% |
0.00% |
3.00% |
|
Land not available for RE Panel works |
11 |
BEAM/SLAB CHERUVATHOOR SIDE |
9 |
7.5 |
1.5 |
0.5 |
0.5 |
0.5 |
0 |
0 |
|
P9-P8 deck slab complete |
12 |
BEAM/SLAB PADANNA SIDE |
8 |
7 |
1 |
complete except railway adjacent span |
|
|
13 |
EXPANSION JOINT CHERUVATHUR SIDE |
9 |
5 |
4 |
0 |
0 |
0 |
0 |
1 |
|
|
14 |
EXPANSION JOINT PADANNA SIDE |
8 |
6 |
2 |
0 |
0 |
0 |
0 |
0 |
|
P1-P6 locations complete |
15 |
KERB CHERUVATHOOR SIDE |
100% |
72.00% |
28% |
0 |
0.00% |
0.00% |
0.00% |
8.00% |
|
|
16 |
KERB PADANNA SIDE |
100% |
80% |
20% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
complete for slab portion |
17 |
HANDRAIL CHERUVATHUR SIDE |
100% |
45% |
55% |
12.50% |
12.50% |
0.00% |
12.50% |
8.00% |
|
complete for AP2-P10 spans |
18 |
HANDRAIL PADANNA SIDE |
100% |
64% |
36% |
0% |
0.00% |
0.00% |
0.00% |
0.00% |
|
AP1-P7 Spans complete |
17 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
18 |
Others |
|
|
|
|
|
|
|
|
|
Drainage works complete for 56 m at chr side. |
19 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
20 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
Date |
28-07-2012 |
29-07-2012 |
30-07-2012 |
31-07-2012 |
01-08-2012 |
02-08-2012 |
03-08-2012 |
######## |
|
|
|
No of labours |
47 |
28 |
35 |
28 |
35 |
5 |
5 |
24 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
available |
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
available |
|
|
|
|
|
|
|
|
|
Cement(bag) |
150 |
100 |
shortage |
|
|
|
|
|
|
|
Steel(MT) |
5 |
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|