   Weekly progress graph as on 03.08.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 19 2 - 0 0 0 0
5 Deck Slab 21 9 12 - 0 1 0 1
  Hand Rails 21 2 19   1 0 1 1
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 28.07.12 30.07.12 31.07.12 01.08.12 02.08.12 03.08.12      
Climate Rain Pleasant Pleasant Pleasant Rain Pleasant      
No. of labours 35 37 35 35 35 30      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 23 m3 26m3              
Coarse Aggregate 35 m3 40 m3              
Cement 120bags 150bags              
Steel 24 MT 28 MT              
 
Back
 
    
STAGING VIEW OF SLAB P11-P12

    
    
DECK SLAB IN P11-P12

    
    
BEAM SHUTTER WORK IN P11-P12

      
 

 

 

 

 

 

 

 