Prevoius Weekly Reports

   Weekly Progress Report as on 27.07.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 63 - - - - - -
2 Pile cap 21 21 - - - - - -
3 Pier  21 21 - - - - - -
4 PierCap 21 19 2 - 0 0 0 0
5 Deck Slab 21 9 12 - 0 0 0 1
  Hand Rails 21 2 19   1 0 1 0
6 RC wall - Kuttipuram side 100% 25% 75% - 0% 0% 0% 0%
                   
Date 21.07.12 23.07.12 24.07.12 25.07.12 26.07.12 27.07.12      
Climate Rain Pleasant Pleasant Rain Rain Pleasant      
No. of labours 38 40 39 40 40 40      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 20 m3 25m3              
Coarse Aggregate 42 m3 45 m3              
Cement 120bags 150bags              
Steel 25 MT 30 MT              
 
Back
 
    
SLAB REINFORCEMENT IN P12-P13

    
    
BEAM SHUTTER SETTING IN P11-P12

    
    
BEAM REINFORCEMENT IN P11-P12

      
 

 

 

 

 

 

 

 